Group Info

Follow-up work after arranging the cabinet

Follow-up work after arranging the cabinet

General steps for network cabinetarrangement:

1. Preparation

First, the user should be notified to organize the cabinet without affecting the user's normal work.

Then according to the topology of the network, the existing equipment situation, the number of users, user grouping and other factors, sketch the wiring diagram and equipment location diagram inside the cabinet.

Next, prepare the required materials: network jumpers, label paper, and various types of plastic ties.

2. Organize the cabinet

Install the cabinet:

You need to do the following three things yourself: first, use the screws and nuts provided with the random frame to tighten the fixing frame; second, pull down the cabinet and install movable wheels; third, according to the location of the equipment Adjust and add the baffle on the fixed frame.

Organize the route:

Group the network cables. The number of groups is usually less than or equal to the number of cable management racks behind the cabinet. Bundle the power cords of all devices together, insert the plugs from the cable holes on the back, and search for their respective devices through a separate cable management frame.

Fixed equipment:

Adjust the baffle in the cabinet to a suitable position, so that the administrator can see the operation of all equipment without opening the cabinet door, and add baffle appropriately according to the number and size of the equipment. Pay attention to leave a certain gap between the baffles. Place all the switching equipment and routing equipment used in the cabinet according to the pre-drawn diagram.

Network cable labeling:

After all the network cables are connected, each network cable needs to be marked. Wrap the prepared sticky notes onto the network cable and mark it with a pen (generally indicate the room number or what purpose it is used for). The identification is required to be simple and easy to understand. The crossover network cable can be distinguished from the general network cable by using sticky notes of different colors. If there are too many devices, classify and number the devices and label them.

3. Later work

UMC test:

After confirming that it is correct, turn on the power and conduct a network connection test to ensure the normal work of the user-this is the most important.

Documentation update:

Document updates on the contents of this cabinet arrangement. Re-draw the equipment layout diagram and network cable connection diagram. The number of the equipment and the identification of the network cable should be indicated on the diagram for inspection and repair. It is best to add the user name as an item to the icon. Finally specify the date and informant.

Hangzhou Dingli is a professional network rack cabinet manufacturer, please feel free to contact us if you need it.

Share:

Users

Newsfeed

  • No items